Manufacturing
Manufacturing Reliability and Lean Transformation
Planning and scheduling redesign, daily management routines and sustainment governance on the plant floor.
- $12.2M
- Annualized savings
- 33%
- Productivity improvement
- 1,338 to 879
- Maintenance backlog reduced
The situation
A manufacturing operation carried a large routine maintenance backlog, low completed work per resource week and high contractor overtime.
The challenge
Improvement practices did not survive contact with the daily schedule. Leadership needed reliability and productivity gains that would still be in place after the improvement team left.
The ISI approach
ISI Consulting Group worked with plant leadership and frontline teams on reliability improvement, planning and scheduling redesign, contractor optimization and Lean transformation.
Implementation
Pull Planning, Pulse Boards, 5S and visual daily management routines were established on the floor.
These were supported by leadership ownership, operational accountability and a sustainment structure of playbooks, governance forums and audit routines.
Results
- Generated more than $12.2 million in annualized savings
- Reduced contractor headcount by 67 personnel
- Reduced routine maintenance backlog from 1,338 work orders to 879
- Improved productivity from 1.5 to 2.0 completed work orders per resource week, approximately 33%
- Reduced contractor overtime and improved utilization
- Established Pull Planning, Pulse Boards, 5S and visual daily management routines
- Strengthened leadership ownership and operational accountability
- Developed sustainment processes, governance forums, playbooks and audit routines
Key services applied
- Performance-Based Implementation
- Operational Excellence
- Lean Transformation
- Maintenance and Reliability
- Planning and Scheduling
- Contractor Optimization
- Visual Management
- Performance Management
- Change Management
- Sustainment Audits
Measured change
Before and after
Routine maintenance backlog
work orders
34% lower
Completed work per resource week
work orders
33% higher
Contractor headcount
67 personnel removed
Figures as published for this engagement.
Next engagement
Schedule quality improved by up to 50% across a pipeline network
Read the engagementRapid Assessment
Two to three days to find where the value is
A focused review of a site, a function or a single operational problem. Leadership receives a fact-based view of the performance gap, the likely value, the immediate priorities and the right next step.